Steve Nichols Channel 13 has raised an interesting question in
his Fox News 13 piece: What
Happens if council can't agree on a Pier design?
Steve explores the issues raised by William Ballard in his Letter
to City Council which is reproduced in its entirety below.
MEMORANDUM
To: The Honorable Charlie Gerdes, Chair, and Members of
City Council of
St.
Petersburg, Florida
From: William C.
Ballard, a resident and registered voter of the City
Date: April 9, 2015
Subject: Options for City
Council in the event the pier design selection committee report to Council accords
the number one ranking to a design concept which was not favored by
the City’s voters (as determined by the City’s own non-scientific survey and
confirmed by St. Pete Polls scientific survey)
The writer is a licensed
attorney in the state of Florida, but he is writing only in his capacity as a
citizen urging a course of action upon his city’s governing body. No reader should regard the writer’s
statements or opinions as legal advice directed at him or her. For advice on the legality of the courses of
action discussed in this memorandum, consult your own attorney.
Under Article III of our municipal charter, all legislative powers are
vested in City Council. The Mayor is the
chief administrative official. City
administration can recommend, only Council can legislate. Based on the conduct, on March 20th,
of the City administration’s representative, who chairs the pier design
selection committee, it appears obvious that City administration is determined
that the inverted pyramid will not remain on our waterfront and that the
selection committee is being steered to achieve that result. The committee chair’s dismissal of all pier
businesses other than those operated by the Gonzmarts as “unsuccessful” despite
many of them having sustained themselves,
supported their owners and employees,
and satisfied pier visitors for over ten years prior to their being forced out
was, in my opinion, an odious misrepresentation of the facts that has prejudiced
the integrity of the selection process.
The form of the resolutions to be recommended to you following the
submission of the 2015 pier design selection committee’s report are likely to
be similar in form to those submitted to Council on February 2, 2012 relating
to the report of the jury of the 2011 Pier International Design
Competition. Both competitions were
conducted pursuant to the Consultants Competitive Negotiation Act (CCNA).
The first resolution submitted in 2012 acknowledged receipt of the
report, confirmed that the jury had completed its duties, and ratified the
jury’s dissolution. The second
resolution approved the jury’s ranking, authorized the mayor to negotiate with
the first ranked team, declared that the A/E agreement would be subject to
approval by Council, and declared the project budget.
Assuming that similar resolutions are submitted to this Council
following submission of a pier design selection committee report, each Council
Member has the power to vote No in response to any motion to approve a
resolution which includes approval of the report and authorization for
negotiations with an A/E team. If the motion
does not command a Yes vote from majority of the Council quorum, this CCNA RFQ
project will have be concluded.
This present CCNA process was initiated by an RFQ issued August 11,
2014. Relevant provisions of this
document include:
·
“All
documents prepared and submitted in response to this RFQ project shall become
the property of the City and the City shall own all ideas, documents and
materials developed in response to this RFQ.
All documents prepared are subject to reuse by the City in accordance
with the provisions of §287.055, Florida Statutes.” [page 67, ¶11]
·
“The
City has the right not to proceed with this project at any time.” [page 17 –
Post Selection]
My own legal research disclosed no published decision under the Florida
CCNA in which an agency (a municipality is an agency under the CCNA) which has
refused to approve a selection committee’s ranking report, has been compelled
to commence negotiation of a design contract or suffered a judgment at the
instance of a design professional. The
CCNA specifies no such remedies. In Board
of Public Instruction v. Doran, 224 So.2d (Fla. 1969), our Supreme Court
stated: “Statutes enacted for the public‘s benefit shall be construed in a
manner most favorable to the public.” A
court would be reluctant to construe the CCNA so as to require a municipality to enter into a contract for
millions of dollars for design services for a project which its governing body
has decided not to build. Moreover, the
City’s contractual right under the RFQ not to proceed is an effective deterrent
to such claims if a project is terminated.
The City has benefited from The New St. Pete Pier Design
Competition. Council and we citizens
have been exposed to visionary concepts for re-use of the inverted pyramid,
partial use of the inverted pyramid’s elements, and novel plans for the pier
and pier uplands. We have cost estimates
for these design concepts. And, as noted
above, the City now owns those concepts.
We know with considerable clarity which of these proposed project
concepts is attractive to a strong majority of residents, and those which are
rejected by a strong majority.
We have learned more. Thanks to
the Terracon report of August 1, 2013 on the condition of the caissons supporting
the inverted pyramid, we know that the concrete is in generally good condition
with no significant physical damage.
The Kisinger Campo & Associates report of August, 2014, provided the
City an evaluation of the inverted pyramid’s steel structure. They found limited corrosion activity after
nearly 50 years in service. They concluded
that extending the design life of the
building structure for an additional 75 years could be achieved with repairs,
reconstruction and other modifications.
This report was part of the package provided the 2015 design contest
participants. Teams with highly
competent engineering consultants concluded that the inverted pyramid could
achieve a new 75 year design life by way of repairs, modifications and new
design features included in their budgets.
Destination St. Pete, for example, will gut the building, replace
interior systems and install a hurricane proof glass skin outside of the
structural frame. That frame, for the
most part, will be within a weather-tight, mostly air conditioned
structure. (Yes, I advocate Destination
St. Pete.)
Lastly, you know more about the direction of the Downtown Waterfront
Master Plan. In three months it will be before you for adoption.
If Council does not adopt a resolution approving the selection committee
report, Council then has the option of clearly defining the pier project it
would have the City build, and then adopting a resolution authorizing an RFQ to
be issued for design services for construction of that clearly defined project.
A project defined in terms of one of the
recent design contest submittals would be a clearly defined project.
If you are forced into this strategy, I urge that you define the project
in terms of the Destination St. Pete Concept. This concept is the one wanted by a great
majority of the people who will pay for this project and, because it would be
their pier, they would be more likely to use it. It was produced by a design team that is
eminent in the true sense of the word.
This concept has minimal impact on DWMP possibilities. Implement this concept and The Pier and Spa
Beach come back to life. The City keeps moving forward.
I also urge that planning commence for a waterfront restaurant site in
Pelican Parking Lot. This is the only
way to achieve the critical mass of visitor activity that happily feeds on
itself. (Read the 2015 Lambert report.) Consider an RFQ for a restaurant development that
includes some retail space, all funded by the developer, with the project
contingent upon a referendum authorizing the developer a lease of sufficient
duration to make the project feasible. This would have to be done in a way that
assures the City’s residents that they are not opening the door to
overdevelopment of the uplands.
I believe this is the path to a successful pier. This path was substantially laid out by the
Pier Advisory Task Force in 2010.
Thank you for considering my
thoughts.
Respectfully,
s/
William
C. Ballard
St. Petersburg, FL 33704
Mayor Kriseman
John Wolfe, City Attorney
Public Distribution
Comment:
Janelle Irwin has an interesting analysis in her saintpetersblog
Post: Latest
development in Pier saga may give City Council more power .
The real news here is the shift of City Attorney John Wolf from
what had been a fairly staunch support of the up or down vote. When questioned
by the Mayor regarding the Ballard letter, according to the Nichol's report,
Wolf replied, "Yes, Mayor they could do that, adding there are other
options for the city council.
The other thing worthy of note is the declining level
professionalism coming from the mayor's office.
Kriseman: "Build the damn Pier"
Kevin King in a tweet to Steve Nichols: @SteveNicholsFOX
@DeniseWhitetv Whole RFQ process; presentations, public outreach, feedback,
rankings, etc. Au Reviour, my friend.
I think we should expect a little more from the million dollar
Kriseman Mayor's office.
With Charlie Gerdes as Chairman and a lot of public scrutiny,
City Council is not going to roll over and create a public fiasco on the Pier. Kriseman
needs to gather it all up, put a lid on his band of lackeys and come to grips
with the fact he is about to go 0 and 2 on the Rays and the Pier.
E-mail Doc at mail
to:dr.gwebb@yahoo.com or send me